Property in the Course of Development
By M. Robert Goldstein and Michael J. Goldstein
From time to time a property is in the course of development
finds itself the subject of a proposed condemnation proceeding.
It may be in the beginning of the process, where planning
is merely taking place or at various stages, up to where construction
is very near completion. It inevitably raises the question
of what the developer should then do, go forward with the
project or stop all activity until the condemnation actually
takes place?
It is not an easy decision. Often the decision is complicated
by the fact that various levels of governmental approval are
required, from variances or rezoning to securing approval
of building plans, and the question arises whether the decision
of the governmental body involved will be influenced by the
pending condemnation, a more than likely proposition, and
what the developer should do about it. What cannot be lost
sight of is that in valuing the property in the condemnation
proceeding the award would probably be negatively affected
if an application for a variance or zone change were turned
down and it could not be proved it was because a condemnation
was pending. Then there are questions relating to losing a
favorable market if he waited and the project did not go forward
and to losing time-limited financing commitments.
We start with the basic proposition that despite a property
being designated for a proposed condemnation proceeding, as
long as the owner continues in title, he has an absolute legal
right to continue to use and develop his property. In fact,
we find a decision that holds that just because a condemnation
proceeding is proposed is no basis for a tenant being relieved
of the obligation under a lease to substantially renovate
a building (2814 Food Corp. v. Hub Bar Building Corp.,
35 AD2d 277, 315 NYS2d 969 [1st Dept., 1970]).
Further, history tells us that, short of actual condemnation,
there is no certainty that a project will go forward. The
proposed Lower Manhattan Expressway and Westway are glaring
examples in a long list of projects that reached various stages
of approval and then were dropped. We have a client who did
not build on a part of his lot on which the State Department
of Transportation told him they were planning to construct
a highway. When the highway was built, the lines had been
changed and it was never taken, with his having lost gainful
use of that part of the property, without compensation.
Stopping the Developer
We also find, on the other side of the process, that, at
least with some condemnors, the temptation to stop the developer
from going forward with his project by extralegal means has
been too great to resist. It happens far more often than most
realize. Thus, it has happened that where an application for
a variance or rezoning or even a building permit was pending,
an unpublicized letter or conversation between agencies or
bodies has led to either the governmental body involved just
sitting on the application without action or unjustifiably
denying it. In the latter instance, the developer at least
has a chance, by an Article 78 proceeding, in doing something
about it, while with the former, unless there are statutory
or regulatory time limits by which the government body must
act, he is helpless.
Sometimes a paper trail has been left when it occurs, but
most times it has not. When there is such a trail we find
the courts act in terms of forcing permits and variances,
disregarding inappropriate zoning and in providing compensation
in the ultimate condemnation award for the resulting loss
(See In re Public School No. 223, City of New York (Nelkin),
71 AD2d 1021, 420 NYS2d 501, aff'd. 51 NY2d 921, 434
NYS2d 981 (1980); In re City of New York (Jomar Real Estate
Corporation) 71 AD2d 1020, 420, NYS2d 501 aff'd 51
NYS2d 921; In re Fifth Avenue Coach Lines Inc., 18
NY2d 212, 273 NYS2d 52 (1966); Keystone Assoc. v. Moerdler, 19 NY2d 78; Bowne v. Town of Hamptonburgh, 76 AD2d
848, 428, NYS2d 526 (2d Dept., 1980); Corrado v. Wolf, 37 Misc2d 89, 235 NYS2d 336 (Meyer J. Sup. Ct. Nassau Co.,
1962); Winpol v. Town of Hempstead, 59 Misc2d 768,
300 NYS2d 197 (Sup. Ct. Nassau Co., Meyer, J.); In re Public
Place, Borough of Manhattan, 54 Misc. 69, aff'd and
remanded 24 AD2d 243, 265 NYS2d 150, on remand __ Misc2d __
, 281 NYS2d 414 rev'd on other grounds 31 AD2d 530; Chase
v. City of Glen Cove, 246 NYS2d 975 (Sup. Ct. Nassau Co.,
Meyer J. 1964); Matter of City of New York (John F. Kennedy
H.S.), New York Law Journal, July 24, 1967, p.10 col.3
(Sup. Ct. Bronx Co., Brust, J.); Zogby v. State of New
York, 53 Misc2d. 740, 279 NYS2d 665 (Ct of Cl., Lengyel,
J., 1967): Oakwood Island Yacht Club v. City of New Rochelle,
59 Misc2d 355, 298 NYS2d 807, aff'd __ AD2d __, 320 NYS2d
505 (2d Dept., 1969); Conway v. Kerr, 51 AD2d 758, 380
NYS2d 44 (2d Dept., 1976); Mt. Morris Assoc. v. McMorran,
35 AD2d. 843, 318 NYS2d 120 (2d Dept., 1970).
Paying Lip Service
Suppose the developer wishes to go forward with his construction
in the face of a planned condemnation, the other side of the
above coin. While we find the courts paying lip service to
his right to do so, unless the developer has the most compelling
reason for continuing with the development their decisions,
in the valuation of the property in the condemnation proceeding,
say something different in the result. We believe this is
the real explanation for the decisions in Matter of City
of New York (Atlantic Improvement Corp.), 28 NY2d 465,
322 NYS2d 708 and Matter of City of New York (G & C
Amusements), 55 NY2d 353, 449 NYS2d 671 (1982), reversing
82 AD2d 829, 439 NYS2d 677.
In the latter case, the amusement rides and ancillary property
in dispute, for which compensation were sought as "trade
fixtures," were held non-compensable "personalty"
by the trial court because, when he installed them, the owner
"gambled" that the property would not be condemned,
he having installed them on land leased from the City, allegedly
in the face of a planned project. They were then deemed compensable
trade fixtures in the Appellate Division, which reversed the
trial court. Then they were held to be part of the real estate,
pursuant to a very strictly construed lease clause, and thus
not compensable to the tenant, in the Court of Appeals.
On oral argument in the Court of Appeals, a year or so later,
in the Jomar case, supra, a case where a building permit
was revoked as to the tenant in the middle of construction
of indoor tennis courts because of a newly planned condemnation
proceeding (restored after a nine-month delay), with the balance
of the development put on hold because of the project, the
other side of the G & C Amusements coin, the then
Chief Judge tacitly acknowledged the reason for its lease
construction in G & C.
It is by reason of these latter decisions and others like
them that we generally advise clients that if they are not
so well along in their development that they have no realistic
chance to halt the process they should put their project on
"hold" until they know whether the condemnation
is going forward. There is a down side to doing so, however.
Usually, there has been a substantial amount of money already
invested in planning, engineering and architect's fees,
while interest on mortgages as well as taxes, insurance and
other costs continue to accumulate while the property remains
unproductive.
There may be time-limited mortgage commitments that will
expire either before the property is condemned or before one
can be sure the project has been abandoned. Then there is
the condemnor that will attempt to attribute the stoppage
of the proposed development to causes other than the planned
condemnation. Sometimes the development is so well along that
it cannot realistically be halted. Sometimes the developer
believes that because his project is so well along and beneficial
he can persuade the potential condemnor to abandon the taking,
usually more a hope than a reality. Sometimes he believes
he can complete the development before a condemnation can
be started.
Favorable Treatment
The upside in halting the work is that the courts appear
to treat those who do so more favorable than those who do
not. The dissenting opinion in the Appellate Division describing
what the trial court included in its award in In re Public
School No. 223 (Nelkin) supra, gives an indication of
what that reaction is:
The total award — included $68,022 for real estate
taxes for the period Jan. 1, 1962, to March 9, 1971, $137,712
for mortgage interest for the same period, $71,071 in architect's
fees, $29,000 in legal fees, and approximately $10,000 in
other fees expended in claimant's attempt to obtain
financing for the projected development of the site.
The underlying facts of the case were that to develop the
project the developer was seeking not only a Federal Housing
Administration mortgage commitment, but a zoning change to
increase density and a real estate tax exemption, which involved
three different agencies. After years of effort, an agreement
was reached to secure all of them. Before it could be implemented,
condemnation of the property was proposed and a letter sent
to the FHA by a City agency asking that it withhold the FHA
mortgage commitment because of the pending condemnation proceeding.
It was complied with.
Nothing happened for more than two years, despite the developer's
efforts, until the property was condemned. Fortunately, the
letter was discovered in the FHA files and put before the
court. While the dissent did not mention this, it appears
that the result in fully compensating the developer for his
out-of-pocket costs was attributed to it. But, we know of
other instances where it is clear something similar happened
but there was no smoking gun.
In Matter of City of New York (New Detention Facility)
(China Plaza Inc.), __ AD2d __ (1989) the Appellate Division
affirmed an award that included the costs of development of
a project that had been halted upon the announcement of a
planned condemnation of the property before it had reached
the actual construction stage but after a package of complete
planning and financing had been completed. While the trial
court never spelled out the exact amount allowed for any particular
item, it indicated it added to the award $3.2 million for
"development costs."
The question then is what the legal justification is for
granting the costs expended in development, besides the moral
and equitable one. The basis alleged has been that the project,
in its then state of development, is saleable as a package
with a buyer securing the advantage of not having to repeat
what has already been accomplished, with its attendant costs,
i.e., it is a project in the course of development (see Arlen
of Naunet v. State of New York, 26 NY2d 465, 322 NYS2d
708; Matter of City of New York (Chestnut Properties Co.),
39 AD2d 573, 332 NYS2d 19 (2d Dept.); Matter of City of
New York (New Detention Facility) (China Plaza Inc.),
supra; Matter of City of New York (P.S. 223) (Nelkin),
supra.
Added Value
While there is always an issue of "reasonableness,"
the actual cost of the work is the best evidence of the value
that the work added to the property. The courts have held
that the cost of construction of a building, "well suited
to its site is some evidence of value, at least as to the
tax years soon after construction" (Joseph E. Seagram
& Sons Ltd. V. Tax Commission, 14 NY2d 314, 251 NYS2d
460 (1st Dept., 1964); Dune Alpine Farm Corp.
v. Assessor of Town of East Hampton, 125 AD2d 672, 509
NYS2d 861 (2d Dept., 1987) and cases cited therein.) This
view is consistent with other aspects of real property valuation
law and recognizes that while the quest is market value, which
may or may not be coincident with the actual cost of construction,
it is similar to using an actual recent lease of the subject
premises as strong evidence of rental value (Matter of
the City of New York (Clinton Urban Renewal-Franklin Record
Center Inc.), 59 NY2d 57, 463 NYS2d 168 (1983); Matter
of the City of New York (Maxwell), 15 AD2d 153, 162, 222
NYS2d 786; c.f. Ettlinger v. Weil, 1184 N.Y. 179, 183; Mater of the City of New York (Marshall), 16
AD2d 570, 229 NYS2d 947 (1962)); a recent sale of the subject
property as strong evidence of its market value, (Matter
of Woolworth Co. v. Tax Commission, 20 NYC 561, 565; Matter
of City of New York (Maxwell), supra); Matter of the
City of New York (Marshall), supra; recent cost of alteration
as strong evidence of added value for a changed use (In
re Madison Houses, 17 AD2d 317, 234 NYS2d 789; In re
P.S. 79, Manhattan, 19 AD2d 239, 241, NYS2d 575); and
actual use as evidence of highest and best use (Matter
of City of New York (Jomar Real Estate Corp.), 61 NY2d
843, 473 NYS2d 963 [1984]). In each instance the actuality,
and otherwise unexplained, is evidence of the first rank.
As the cases make clear, existence does not make it conclusive
but shifts the burden of proof to the side contending differently.
While this is an over simplification of a larger subject,
it is clear from a synthesis of case law that there is a basic
presumption in law of the reasonableness of an actual transaction.
While it is specifically stated and recognized that no single
transaction bespeaks and entire market, and the fact of actuality
as to the subject property does not preclude other evidence
inconsistent with that fact to prove the market to be otherwise,
the fact itself, unless otherwise explained, is evidence of
the first rank in determining market value of the subject
property. This being so, if the cost of a building recently
completed is evidence of the first rank, then the cost of
development of a building in the process of development is
also evidence of the first rank of the value.
Since actual cost is evidence of the first rank as to value,
what then is included as part of the cost. As was stated in Matter of City of New York (Harlem-East Harlem Neighborhood
Development Area-Salvation Army Inc.), 43 NY2d 512, 516,
402 NYS2d 804, 805 (1978):
Implementation of the summation method requires the inclusion
not only of payments for material, equipment, labor and
other obvious physical ingredients which go directly into
construction, but also of those charges which may be termed
indirect or less direct, such as architect's fees,
contractor's profits, interest and taxes on land
during the period of construction, cost of procuring necessary
licenses and the miscellany of other essential overhead
or incidental expenses. For a fair and realistic appraisal
of reproduction costs must embrace in its reckoning all
expenditure that reasonable and necessarily are to be
expected in the re-creation of a structure so idiosyncratic
as to leave no alternative method by which to measure
fair compensation. (Cases cited)
Financing costs are such an expenditure (citation). —
Thus, whether an owner uses its own or borrowed funds,
the calculation of true cost would, wither way, require
inclusion of costs of financing.
See also D'Amico v. State of New York, 37 AD2d
681, 323 NYS2d 224 (4th Dept., 1971); Richards
"Of Course" Inc. V. State of New York, 36 AD2d
572, 317 NYS2d 827 (4th Dept., 1971); Lapides
v. State of New York, 37 AD2d 755, 323 NYS2d 179 (4th Dept., 1979); Ryan v. State of New York, 39 AD2d 830,
333 NYS2d 158 (4th Dept., 1972); Rustcon Developers
v. State of New York, 33 Ad2d 582, 3304 NYS2d 287 (3d
Dept. 1969); Salamone & Company v. State of New York, 40 AD2d 916, 337 NYS2d 846 (3d Dept., 1972); Specialty
Foods Corp. v. State of New York, 46 AD2d 989, 362 NYS2d
266 (3d Dept., 1974); In re City of New York (North Central
Brooklyn High School-Chestnut Properties Co.), 39 AD2d
573, 332 NYS2d 19 (2d Dept., 1972), aff'd, 34 NY2d 800,
359 NYS2d 40); (See also Internal Revenue Code, §189,
which provides that interest and taxes for purposes of acquiring,
constructing and carrying real property during the construction
period is not deductible as an expense but must be capitalized).
In Banner Milling Co. v. State of New York, 240 N.Y.,
533 the court, while referring to "fair value of architect's
and engineer's fees upon the construction and equipment
of said plant, insurance premiums and interest on investment
during construction period, railway franchises, legal expenses,
sundry items correcting errors in construction expenses incurred
in operating the mill at a loss up to a time when machinery
is synchronized and coordinated so as to produce a satisfactory
result" stated, at page 545, that while claimant was
not entitled as a matter of law to recover for those expenses
they were entitled to have them considered. As the court said
(P. 546):
Each case necessarily involves different facts and must
be considered by itself. Only a few general rules apply
on the question of valuation in condemnation proceedings,
and even these may yield to exceptional circumstances.
The rule in condemnation proceedings is "just compensation."
Fair market value is only a means of getting to it. But exceptional
facts require exceptional handling.
Before we leave this subject, we mention one other aspect
of this problem that the courts are yet to address and that
the appraisal texts have just begun to recognize. That is
compensation for earned "entrepreneurial profit."
It is a subject that is inherent in the compensation to be
awarded for property in the course of development. Developers
build for profit. That being so, the project, when completed,
should be worth more than merely the land value plus the actual
costs of construction, both hard and soft costs and builder's
overhead and profit. That difference is the entrepreneurial
profit. As was stated in Levin v. State of New York, 13 NY2d 87, 242 193 (1963):
— Nor would one expect the prospective purchaser
to pay for the vacant land in suit an amount equal to
the worth of the conjectured net rental income, deducting
of course, construction and other costs necessary to complete
the building — for, then, he would be paying an amount
which would precluded any profit. What the purchaser would
pay would undoubtedly be influenced by the extent to which
the property had been exploited.
If the project had been completed it would have included
within its value that entrepreneurial profit. The question
then is why should not a project in the course of development,
which is only partially completed, have included as part of
its value more than just the land and money expended, but
a proportionate part of the entrepreneurial profit that condemnation
has deprived him from realizing. For the same reason, one
cannot come to a land value by contemplating the value upon
completion and only deduct the costs of development without
deducting for "entrepreneurial profit," (the so
called "residual" approach to land value), one should
not merely be limited to land value plus development costs
where there is a property in the process of development without
including an amount for that part of the entrepreneurial profit
earned to that stage of the development. Reprinted with permission from the March 18, 1992 edition of the New York Law Journal © 2010 Incisive Media Properties, Inc. All rights reserved. Further duplication without permission is prohibited.
Back to first page of publications
|